Your local councillors recently attended an update briefing from Surrey CC’s Transport Strategy Project Manager and Transport Planner on the work planned to provide improved pedestrian and cycling paths from Weybridge town centre to the station and through to Brooklands Park. 

Some preparatory work has already been completed:

  • Last summer clearing of ground-covering scrub and trees was undertaken along Heath Road; a few trees were retained to give a better aesthetic and the paths will be routed around these. 
  • The much-needed resurfacing of St George’s Avenue last October was also part of the scheme and a dropped kerb was built towards the station end of the road so that cyclists can come off the road onto a short section of pavement to then cross the main road via the refuge.
  • In November, the refuges for pedestrian access to the station were widened and dropped kerbs improved.

More work is planned for the February half-term, including larger refuges for the crossing on Brooklands Road to Heath Road South car park. Following this, the track from the car park, past the sewage treatment works, across the River Wey and through to Brooklands will be widened and provided with lighting. Funding has been ear-marked for improvements to Sopwith Drive and Wellington Way as well as for better pedestrian access to the station and for increased cycle parking provision. There will be bus stop improvements and suitably placed finger-post signs. The path under Wellington Way occasionally floods, as it has done recently, and a raised boardwalk is planned to keep this path open and usable more often.

If there is sufficient money then a second phase will be considered to link the planned route from Heath Road through to Churchfields and the town centre. This exciting proposition would complement the current discussions of a town regeneration scheme centred around developing the publicly-owned NHS, library and community centre sites. There would be further public consultation on any proposed options.

This website uses cookies

Like most websites, this site uses cookies. Some are required to make it work, while others are used for statistical or marketing purposes. If you choose not to allow cookies some features may not be available, such as content from other websites. Please read our Cookie Policy for more information.

Essential cookies enable basic functions and are necessary for the website to function properly.
Statistics cookies collect information anonymously. This information helps us to understand how our visitors use our website.
Marketing cookies are used by third parties or publishers to display personalized advertisements. They do this by tracking visitors across websites.